Project objectives should be determined and conveyed by which party in a project?

Prepare effectively for the WGU MHRM6020 D435 HR Technology and People Analytics Exam. Use our flashcards and multiple choice questions with hints and explanations to boost your confidence. Ace your exam!

The correct answer is that project objectives should be determined and conveyed by the project sponsor. The project sponsor plays a crucial role in establishing the vision and goals for a project. They are typically a senior individual within the organization who has the authority to allocate resources and make decisions that affect the project's direction.

Having the project sponsor identify and communicate the objectives ensures that the project aligns with the organization's strategic goals and priorities. This alignment is vital for the success of the project because it establishes a clear purpose and framework within which the project team can operate. When the project sponsor outlines the objectives, it also facilitates clear communication and understanding among all involved parties, thereby minimizing potential misunderstandings later in the project.

Although other parties, such as stakeholders and clients, may provide input and express their needs, it is ultimately the project sponsor who is responsible for distilling this information into clear, actionable objectives that guide the project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy