Which dependency requires a specific sequence for tasks to maintain project integrity?

Prepare effectively for the WGU MHRM6020 D435 HR Technology and People Analytics Exam. Use our flashcards and multiple choice questions with hints and explanations to boost your confidence. Ace your exam!

The choice regarding Finish-to-Start Relationships reflects a foundational principle in project management, particularly when addressing task dependencies. This particular dependency requires that one task must be finished before another can begin. This sequence is crucial because it ensures that the prerequisite work has been completed, which maintains the integrity of the project workflow. Projects often involve complex interdependencies; therefore, adhering to a specific order helps to avoid disruptions that might arise if tasks were performed out of sequence.

For instance, in a construction project, the foundation (task one) must be completed (finished) before the walls (task two) can be constructed (started). This control is vital as it minimizes risks and inefficiencies, ensuring that each phase of the work is completed satisfactorily before beginning the next, ultimately preserving the project’s integrity.

Other types of dependencies, such as discretionary dependencies, may inform project sequencing based on best practices or preferences rather than strict necessity, and physical dependencies refer to those that are based on physical or logical constraints. Concurrent activities imply tasks that can occur at the same time without waiting for each other. However, none of these demonstrate the necessity of maintaining a specific sequence to uphold the project structure as clearly as Finish-to-Start Relationships do.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy