Which statement best describes the triple constraint concept?

Prepare effectively for the WGU MHRM6020 D435 HR Technology and People Analytics Exam. Use our flashcards and multiple choice questions with hints and explanations to boost your confidence. Ace your exam!

The statement that changes to one constraint affect the other two best describes the triple constraint concept. The triple constraint, also known as the project management triangle, highlights the interrelationship between three primary constraints of any project: scope, time, and cost. When one of these constraints is altered, it inevitably impacts the other two. For example, if the scope of a project increases, it would likely lead to increased costs and extended timelines to accommodate the additional work. Similarly, if a project’s timeline is shortened, it may require either a reduction in scope or an increase in cost to meet the new deadline. This interdependence illustrates why project managers must carefully balance these constraints to ensure project success.

The other options do not accurately capture the essence of the triple constraint. For instance, suggesting that all project tasks are equally important overlooks the prioritization that is often necessary due to the finite resources and constraints of time and budget. Claiming that cost is the only factor influencing project success is an oversimplification, as successful project management must consider all three constraints working in harmony. Lastly, declaring that time management is irrelevant to project execution contradicts fundamental project management principles, where effective time management is crucial for aligning tasks with project goals and deadlines.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy